Metrolinx questioned by CTF as Ontario line costs rise

GO Transit trains.
GO Transit trains. Photo by VERONICA HENRI /TORONTO SUN FILES

Metrolinx can’t be relied on to produce the new Ontario Line on time and on budget, the Canadian Taxpayers Federation (CTF) says.

CTF Ontario Director Jay Goldberg said the latest cost estimate for the new Toronto transit line is at least $19 billion, up from $11 billion, a 75% increase when the project is still in its earlier days.

As the Canadian national soccer teams head to their respective FIFA World Cups, Derek Van Diest is on the scene to cover all the action. Expect expert insights and analysis in your inbox daily throughout the tournaments, and weekly on Thursdays for the rest of the season.

By clicking on the sign up button you consent to receive the above newsletter from Postmedia Network Inc. You may unsubscribe any time by clicking on the unsubscribe link at the bottom of our emails. Postmedia Network Inc. | 365 Bloor Street East, Toronto, Ontario, M4W 3L4 | 416-383-2300

“That’s eight brand new state-of-the-art hospitals,” Goldberg said Tuesday. “I think it’s a real failure on the part of Metrolinx in terms of management … It’s definitely time for the Ford government to look at whether Metrolinx really is the best vehicle to be delivering these projects and it seems like the answer is no.”

The Ontario Line would be a 15.6-kilometre, 15-stop line from the Ontario Science Centre through the downtown to Exhibition Place.

Dakota Brasier, a spokesperson for Ontario Transportation Minister Caroline Mulroney, said the government has tasked Metrolinx with delivering the largest transit expansion plan in Canadian history.

  1. A Metrolinx Eglinton Crosstown Light Rapid Transit train is rolled out on Aug. 27, 2001 along a stretch of Eglinton Ave. E. through the 'Golden Mile' section of Scarborough from Victoria Park.

    LILLEY: Metrolinx dodges questions on close ties to private consultant

  2. Go Transit trains.

    Metrolinx looks at three-strike fine system for riders who don't pay fare

“Construction projects worldwide are facing economic challenges with rising inflation costs and supply chain shortages,” Brasier said. “We are making significant progress on the Ontario Line and will continue to ensure that Ontario taxpayers receive the best value for their money possible.”

Goldberg said there needs to be ongoing transparency around the cost of this and other major infrastructure projects so Ontario residents can determine if the high cost is the best use of their money or whether they would prefer the funds spent on other priorities.

“For people at home, people looking at the sticker cost … what else could we be getting for $19 billion,” he said. “When a lot of people hear that the cost of this project has nearly doubled, it’s nowhere near completion, it is just one of the many projects the Ford government is pursuing that will end up costing us well over $30 billion … you have to ask what could we be getting for this instead?”